The prediction of sediment deposition in the foundation trench is mainly aimed at the construction needs of deep and medium channel engineering. Based on the numerical simulation prediction system, it mainly lists the predicted thickness of sediment deposition in the foundation trench during the sinking construction period of 9 pipe sections E1-E9. The forecast provides important support for the decision-making and construction organization of immersed tube construction. From the actual results, it can be seen that the predicted values accurately provide a judgment on whether the design requirements are met, providing accurate basis for construction.
The data time range is from June 2020 to April 2021, during the sedimentation construction period of E1-E9 pipe sections. Each forecast is based on the construction organization arrangement, predicting the daily and cumulative sediment deposition thickness between the start of gravel leveling and the completion of sinking construction.
| collect time | 2020/06/01 - 2021/04/30 |
|---|---|
| data size | 811.3 KiB |
| data format | |
| Data time resolution | day |
Generated based on numerical simulation forecasting system.
Computational simulation.
The data quality is good.
| # | number | name | type |
| 1 | 2018YFC0809600 | National key R & D plan |
This work is licensed under
CC BY 4.0 (Creative Commons Attribution 4.0 International License).
| # | title | file size |
|---|---|---|
| 1 | 基槽泥沙淤积预报.pdf | 793.4 KiB |
| 2 | 数据集说明文件.docx | 17.9 KiB |
Deep and medium channel construction period submarine tunnel foundation trench sediment deposition prediction
i2v5ec
k2bhJL-N
©Copyright 2005-. Northwest Institute of Eco-Environment and Resources, CAS.
Donggang West Road 320, Lanzhou, Gansu, China (730000)